Govt move turns the screw on Rio Tinto

By bringing forward over $100 million of transmission line upgrades, thus lessening the impact of a closure of Tiwai Point smelter, the Government has reduced Rio Tinto's leverage over it.

The Government has turned the screw up another notch on Rio Tinto to keep Tiwai Point open by bringing forward over $100 million of transmission line upgrades by a year so Manapouri's electricity can be fed into the South Island's grid.

Transpower announced yesterday it had agreed with Contact and Meridian to begin work immediately on the remaining three projects in a five-project plan to better connect the power produced at Manapouri into the South Island grid.

Two of the five projects were done between 2010 and 2016, but were the other three were suspended in 2016 after the previous Government secured Tiwai Point with a $30 million payout. The early resumption means the work can start this summer and be completed by June 2022, rather than June 2023.

Contact CEO Dennis Barnes said Contact would provide $5 million in pre-funding to accelerate the work and he welcomed Transpower's "flexibility and pragmatism."

"Our view remains that a disorderly exit of the smelter would be a poor outcome for New Zealand. Sudden closure will affect multiple stakeholders, including all generator retailers. It would also be detrimental to the Southland economy and the pursuit of our decarbonisation goals," Barnes said.

Meridian CEO Neal Barclay said Meridian, which sells the majority of the power for the Bluff aluminium smelter, would also provide $5 million of pre-funding.

"Once the remaining works are complete, it will alleviate existing constraints and significantly reduce the risk of renewable electricity not being dispatched, should Rio Tinto choose to close its Tiwai Point aluminium smelter in the future," Barclay said.

The early transmission investment reduces the leverage Rio Tinto might have, given the risks that not all of Manapouri's power could be fed into the grid if the smelter closed, given the existing infrastructure in place.

However, more work would need to be done to feed the power to the North Island and Auckland in particular, as Transpower explains in this useful Q+A on the CUWLP project. That work would include another $500 million of work, including a fourth HVDC line across the Cook Strait.

Get it early – This article was first published on Newsroom Pro and/or included in Bernard Hickey’s ‘8 Things’ morning email of the latest in-depth business and political analysis. Get it early by subscribing now or starting a 28-day free trial.

Help us create a sustainable future for independent local journalism

As New Zealand moves from crisis to recovery mode the need to support local industry has been brought into sharp relief.

As our journalists work to ask the hard questions about our recovery, we also look to you, our readers for support. Reader donations are critical to what we do. If you can help us, please click the button to ensure we can continue to provide quality independent journalism you can trust.

Comments

Newsroom does not allow comments directly on this website. We invite all readers who wish to discuss a story or leave a comment to visit us on Twitter or Facebook. We also welcome your news tips and feedback via email: contact@newsroom.co.nz. Thank you.

With thanks to our partners